CONSTRUCTION, REMODELING AND REFURBISHMENT OF LAND ADMINISTRATION BUILDINGS AT JINJA AND MBALE DISTRICTS-

Contract Award

General Information

Country:   Multi-country
City/Locality:   Kampala
Notice/Contract Number:   IFB No PSFU/PSCPII/IFB 05W
Publication Date:   Jun 10, 2010
Funding Agency:   World Bank
Buyer:   UG-Priv Sec Competitiveness 2
Eligibility of Bidders:   (a) An average annual volume of construction work over the past five years of at least: Ushs. 1.20 billion.
(b) Experience as prime contractor in the construction of at least five construction projects of a nature and complexity equivalent to the work bidded for. This experience should cover a period of five years. (to comply with this requirement, works cited should be at least 70 percent complete);
(c) Proposals for the timely acquisition (own, lease, hire, etc.) of the essential equipment:
Equipment type and characteristics
Minimum number required
1. Carpentry equipment set 1
2. Standard Scaffolding (100sq.m) 2
3. Metal fabrication set 1
4. Truck 7 Ton 2
5. Water tank vehicle 7000Lt 1
6. Diesel Generator 100KVA 2
7. Diesel compressor 125/175 2
8. Dumper 1 Ton 2
9. Concrete mixer Lt. 350, 500 2
10. Vibrator Roller 2 Ton 1
11. Diesel /Electrical concrete vibrators 2
12. Welding machine 300AMP 2

(d) A Contract Manager with five years’ experience in works of an equivalent nature and volume, including no less than three years as Manager; and
(e) Liquid assets and/or credit facilities, net of other contractual commitments and exclusive of any advance payments which may be made under the Contract, of no less than: Ushs. 150 Million
Original Language:   English

Contact Information

Address:   Michael Wong
Sr. Private Sector Spec.
Mirambo House 50
Dar Es Salaam P.O Box 2054
Tanzania
Telephone:   255 22 2114575
Fax:   255 22 2113039
Email:   Click here

Goods, Works and Services

 

Original Text

     view in:

Name of Project: Second Private Sector Competitiveness Project in Uganda
Project ID: P083809
Contract Description: The Construction of Jinja and Mbale District Land Offices
Duration: 8 Months
Contract Signature Date: June 2010



No. Bidder Read-out Bid Price(s) Rejected Bids and Reasons for Rejecting them Evaluated Bid Prices Contract Award
Name Lot Cur Amount(s)
1 Excel Construction Limited 1 Shs 1,015,148,566 Cost was high 1,015,124,818
2 Shs 949,756,758.00 Cost was high 948,601,539
2 Lamba Enterprises Ltd 1 Shs 815,089,581.40 Signatory to the bid did not have powers of attorney NA
2 Shs 761,218,168.20 NA
3 Nexus Uganda Limited 1 Shs 744,342,113.00 Bidder does not minimum post qualification criteria 744,382,163
4 Broadway Engineering Services Limited 1 Shs 748,209,986.00 Bidder does not minimum post qualification criteria 771,573,986
2 Shs 693,617,508.00 693,617,508.00 √
5 BMB Construction Limited 1 Shs 666,844,715.00 Bidder does not minimum post qualification criteria 710,092,816
6 Kol Services Limited 2 Shs 767,905,334.00 Cost was high 767,905,334.00
7 Honest Contractors 1 Shs 690,433,393.00 Bidder provided an invalid bid security NA
2 Shs 756,178,034.00 NA
8 Home Builders Limited 1 Shs 756,037,012.00 Bidder provided an invalid bid security NA
2 Shs 709,238,382.00 NA
9 Babcon Limited 1 Shs 776,609,899.00 Bidder provided an invalid bid security NA
2 Shs 755,868,056.00 NA
10 Eastern Builders and Engineers Limited 1 Shs 869,293,968.00 Signatory to the bid did not have powers of attorney NA
2 Shs 830,053,785.00 NA
11 Pioneer Construction Limited 1 Shs 842,644,855.80 842,644,855.80 √
2 Shs 789,041,350.00 Cost was high 788,153,518
Please note that this notice is for your information only.
We try our best to have the most accurate and up-to-date information available on our web site, but we cannot guarantee that all of the information provided is error-free.
If you have any suggestions for updates/corrections for this notice, please let us know.