AM-Metsamor: INSC — operation of the emergency core cooling system in long-term cooling mode for Armenian NPP (A1.01/08 T1)

Prior Information Notice

General Information

Country:   Armenia
City/Locality:   METSAMOR
Notice/Contract Number:   eu:120151-2010
Publication Date:   Apr 12, 2011
Deadline:   Apr 27, 2011
Buyer:   ARMENIAN NUCLEAR POWER PLANT
Original Language:   English

Contact Information

Address:   ARMENIAN NUCLEAR POWER PLANT
METSAMOR
Armenia

Goods, Works and Services

 

Summary

     view in:

Notice Type: AP500 - Prior Information Notice
Regulation of Procurement: PHARE, TACIS and countries of Central and Eastern Europe
EU Official Journal Publication: 81/2010, #120151-2010
Contract Nature: Supply contract
Procedure Type: Prior information or periodic indicative notice
Type of Bid Required: Not defined
Awarding Criteria: Not defined


Update: Apr 12, 2011


Notice type: AP2EC - Additional information
Regulation of Procurement: PHARE, TACIS and countries of Central and Eastern Europe
EU Official Journal Publication: 71/2011, #114152-2011
Referenced Document Number: 120151-2010
Contract Nature: Supply contract
Procedure Type: Prior information or periodic indicative notice
Type of Bid Required: Not defined
Awarding Criteria: Not defined

Original Text

     view in:

Armavir Region — Republic of Armenia
Individual supply contract forecast
1. Publication reference:
EuropeAid/129991/D/SUP/AM.
2. Procedure:
Open.
3. Programme:
Instrument for Nuclear Safety Cooperation (INSC).
4. Financing:
Action programme 2008.
5. Contracting authority:
Armenian Nuclear Power Plant, Metsamor, REPUBLIC OF ARMENIA.
6. Contract description:
The objective of this project is the modification of the ANPP emergency
core cooling system (ECCS). The modification shall ensure reliable
operation of the ECCS in any pressure conditions in primary circuit. It
will include modification of the ECCS pumps discharge line in the
following way:
— delivery and installation of the set of the valves and devices for ECCS
pumps in order to control the flow of the ECCS in all reactor installation
operational modes,
— delivery and installation of the corresponding I&C devices.
7. Indicative number and titles of lots:
1 lot.
8. Intended timing of publication of the procurement notice:
Second semester 2010.
9. Additional information:
None.
10. Legal basis:
Council Regulation (Euratom) No 300/2007 of 19.2.2007 establishing an
Instrument for Nuclear Safety Cooperation.
Remarks:
There must be a minimum period of 30 calendar days between the publication
of this contract forecast and the publication of the corresponding
procurement notice.
No applications or requests for further information should be sent at this
stage.




Armavir Region — Republic of Armenia
Cancellation of an individual supply contract forecast
(Supplement to the Official Journal of the European Union, 27.4.2010,
2010/S 81-120151)
1. Publication reference:
EuropeAid/129991/D/SUP/AM.
2. Date of publication:
27.4.2010, OJ S 81.
3. Programme:
Instrument for Nuclear Safety Cooperation (INSC).
4. Contracting authority:
Armenian Nuclear Power Plant, Metsamor, REPUBLIC OF ARMENIA.
5. Other information:
Should a new tender procedure be launched for this project, a new forecast
notice will be published.
Natural or legal persons interested should not therefore send proposals or
requests for information at this stage.




Please note that this notice is for your information only.
We try our best to have the most accurate and up-to-date information available on our web site, but we cannot guarantee that all of the information provided is error-free.
If you have any suggestions for updates/corrections for this notice, please let us know.