RS-Pristina: IPA — construction of Ferizaj 2 400/110 kV substation and connection in the transmission grid

Prior Information Notice

General Information

Country:   Serbia
City/Locality:   PRISTINA
Notice/Contract Number:   eu:314056-2008
Publication Date:   Dec 5, 2008
Buyer:   THE EUROPEAN UNION
Original Language:   English

Contact Information

Address:   THE EUROPEAN COMMISSION LIAISON OFFICE TO KOSOVO
PRISTINA
Serbia

Goods, Works and Services

 

Original Text

     view in:

Notice Type: 0708
-
Prior Information Notice
Regulation of Procurement: PHARE, TACIS and countries of Central and Eastern Europe
EU Official Journal Publication: 237/2008
, #
314056-2008
Contract Nature: Works
Procedure Type: Prior information or periodic indicative notice
Type of Bid Required: Not defined
Awarding Criteria: Not defined

Summary:
Location — Ferizaj area, Kosovo UNSCR 1244
Works contract forecast
1. Publication reference: EuropeAid/127846/D/WKS/KOS.
2. Procedure: Open international.
3. Programme: IPA.
4. Financing: IPA 2008 with co-financing from Kosovo Consolidated Budget
(KCB).
5. Contracting authority: The European Commission Liaison Office to
Kosovo, Pristina, Kosovo.
6. Description of the contract: The purpose of this project is to upgrade
the transmission network in Kosovo by increasing the 110 kV capacity and
improving the quality of supply.
The project includes the following activities: design, manufacturing,
supply, construction of a new Ferizaj 2 (400/11 kV) substation and related
overhead lines and adaptation works in 2 existing substations (Bibaj and
Gjilan 1), site testing and commissioning.
The new Ferizaj 2 substation will be located in the area of Ferizaj about
40 km from Prístina, Kosovo.
7. Indicative number and titles of lots: Lot 1— design, manufacturing,
supply, construction and commissioning of Ferizaj 2 substation and supply
of two additional 110 kV bays and related adaptation works at the existing
Bibaj and Gjilan 1 substations.
Lot 2 — design, manufacturing, supply, construction and commissioning of
overhead lines for connection of Ferizaj 2 substation in the 400 kV and
110 kV transmission network.
8. Scheduled publication date of the procurement notice: February/March
2009.
9. Other information: Not applicable.
10. Legal basis: IPA Council Regulation (EC) No 1085/2006 as adopted on
17.7.2006.
Remarks:
There must be a minimum period of 30 calendar days between the publication
of this contract forecast and the publication of the corresponding
procurement notice. No applications or requests for further information
should be sent at this stage.


Please note that this notice is for your information only.
We try our best to have the most accurate and up-to-date information available on our web site, but we cannot guarantee that all of the information provided is error-free.
If you have any suggestions for updates/corrections for this notice, please let us know.